Installing cavity wall ties in masonry walls

Whilst correct design, specification and detailing of cavity wall ties is important; correct and quality installation is just as critical to ensure performance of a wall throughout the life of a building.

Incorrect specification or installation can lead to moisture ingress or potential structural failure of the masonry wall panels.

Building Regulation 7(1) requires building work to be carried out in a workmanlike manner, with adequate and appropriate materials to perform the functions for which they are designed.Approved Document Regulation 7gives guidance on demonstrating material performance and refers to the BS 8000 series for more detail on building site workmanship.

Installation of cavity wall ties should always be undertaken in accordance with any manufacturers instructions or guidance, especially where they are a proprietary or special product. However, some general rules on installation should be followed in all situations unless the manufacturers' details give an alternative approach.

This article only relates to buildings having a top floor level that is less than 18m from the lowest external ground level.

Correct wall tie specification

It is important that the product is suitable for the situation proposed. Using a wall tie at variance to the specification must be approved by the designer or structural engineer after they have reviewed the product and confirmed its suitability in the situation.

Any wall ties used should be compatible with any retaining clips used for partial fill cavity insulation. Advice should be sought from the manufacturers to ensure compatibility.

If there is any uncertainty, the specification must be checked with the designer.

Paragraph 2C19 and Table 5 of Approved Document Agives the specification of cavity wall ties for certain smaller buildings, confirming these should be austenitic stainless steel and type 1, 2, 3 or 4 in accordance with BSI PD 6697:2010.

Guidance within Paragraphs 2.18-2.24 of Approved Document E should also be consulted to ensure suitable cavity wall ties are used within separating and external cavity walls for the resistance to sound transmission.

Thermal performance and wall ties

Wall ties can affect the thermal performance of an external wall and as a result may need to be considered when undertaking a U-value calculation.

U-value calculations should be assessed using the methods and conventions set out in BR443, published by the BRE.

In this document it states that U-values may need to be corrected where mechanical fasteners (e.g. wall ties) penetrate an insulation layer as detailed in Annex F of BS EN ISO 6946. However, BS EN ISO 6946 permits wall ties (for the purposes of thermal calculations) to be omitted if:

Otherwise, the effect of wall ties needs to be considered when calculating the U-value of a masonry wall. The correction requires knowledge of the thermal conductivity of the wall ties, their cross-sectional area, the number per square metre of wall and the thickness of insulation which is penetrated by the wall ties.

In the absence of exact details, BR443 provides guidance on typical thermal conductivity () data and also provides guidance on typical cross-sectional areas of wall ties.

Installation of wall ties

BS 8000-3 (code of practice for masonry) provides standards on good workmanship for the installation of cavity wall ties in masonry wall construction. It's important that designers, installers, site managers and verifiers of construction are familiar with the recommendations to avoid potential failures.

Wall ties should be installed by following the recommendations in Diagram 1 below so that:

Diagram 1 : Correct wall tie installation methods

Diagram 2 (below) highlights some of the ways that cavity wall ties should not be installed:

Diagram 2: Incorrect wall tie installation methods

Spacing of ties

The approved design specification should always be followed. For masonry cavity walls with each leaf at least 90mm, Approved Document Aand BS 8000-3 recommends that the wall ties should have a horizontal spacing of 900mm maximum and a vertical spacing of 450mm maximum as illustrated in Diagram 3. Alternatively, they can be spaced so that the number of wall ties per square metre is not less than 2.5 ties/m.

Wall ties should also be spaced not more than 300mm apart vertically and within 225mm from the vertical edges of all openings (Diagram 3), roof verges (Diagram 4) and movement joints.

Diagram 3: Wall tie spacing

Diagram 4: Wall tie spacing at gable roof verges

If in doubt, correct specification and installation should be checked with the designer or site manager and further verified with the Local Authority Building Control team where changes from any approval are proposed.


Disclaimer:

Every care has been taken to ensure that the above content is correct at the time of publication. Any reliance on the content should be verified by the dutyholder(s) and their professional advisers. It is the responsibility of the dutyholder(s) and/or person carrying out the work to ensure compliance with the relevant building regulations and associated legislation.