What is SAP?

The Standard Assessment Procedure for the Energy Rating of Dwellings (SAP) is the UK Governments National Calculation Methodology for assessing the energy performance of dwellings. SAP was developed by BRE and first published in 1993.

Over the years is has been updated multiple times including 1998, 2001, 2005, 2009 and 2012. The most recent version is SAP 10.
SAP 10 calculations consider a range of factors that contribute to energy efficiency within a new dwelling, such as:

SAP 10 calculations relate only to the performance of a dwelling. As a result, SAP 10 calculations are independent of factors related to the individual characteristics of the occupants, such as:

How is SAP used to show compliance with Part L?

A new dwelling must be built to a minimum standard of energy performance. This is evaluated by comparing calculations of the performance of the actual dwelling against calculations of the performance of a theoretical dwelling called the notional dwelling. This must be carried out both at the design stage and when the work is complete.

The notional dwelling is the same size and shape as the actual dwelling and has standardised properties for fabric and services. The full properties of the notional dwelling are set out in SAP 10.

Approved Document L Volume 1: Dwellings (2012 edition) states that the energy performance of the notional dwelling is described using the following metrics:

The target primary energy rate, target emission rate and target fabric energy efficiency rate for individual dwellings must be calculated using the reference values in Appendix R of SAP 10.

SAP 10 also calculates some other indicators of energy performance, including:

Transitional arrangements

The use of Approved Document L Volume 1: Dwellings (2012 edition), and therefore SAP 10, took effect from 15 June 2022. However, it does not apply to work subject to a building notice, full plans application or initial notice submitted before 15 June 2022, provided the work starts onsite before 15 June 2023. The transitional arrangements are summarised below:

Application date

/ Works commence

Before
15 June 2022
After
15 June 2022
Before
15 June 2023
SAP 2012SAP 10
After
15 June 2023
SAP 10SAP 10

Table 1: Summary of transitional arrangements

Recent changes to SAP

In 2017, the Department for Business, Energy & Industrial Strategy (BEIS) released a public consultation to detail proposals to amend SAP 2012. Based on this consultation, in July 2018 the BRE published their first version of SAP 10.

The present version of SAP 10 is 10.2, and the BRE list the main changes from SAP 2012 as follows:

Some of these changes will now be considered in slightly more detail.

Fuel prices and CO2 emissions

Table 2 below summarises the changes relating to assumed unit price of energy and their associated CO2 emission.

Table 2: Fuel prices and CO2 emissions

What does this mean for you?

SAP 10.2 has significantly reduced the carbon emissions of electricity to 0.136 kgCO2/kWh (averaged over a year) this is a reduction of 73.8% over the emissions assumed in SAP 2012. This reflects the increased influence of renewable energy technologies producing electricity for the national grid and its continued de-carbonisation. When considering the most widely accessible fuel sources available to occupants of dwellings, this now means that electricity is considered one of the least carbon intensive fuel sources.

SAP 10.2 calculates fuel prices by averaging them over the previous three years and across regions. However, the Government indicated, in the Future Homes Standard Consultation that they may consider making changes to future versions of SAP to ensure that fuel prices are updated annually. This is particularly important given the recent fuel inflation.

Thermal bridging

In SAP 2012, there were three options for calculating thermal bridging, as detailed below:

SAP 10.2, has updated the above options as detailed below:

Further details on changes to thermal bridging in SAP 10.2 can be found in the SAP 10 Technical Paper (S10TP-05) published by BRE.

What does this mean for you?

Designers and builders will be encouraged to calculate the actual junctions and resultant thermal bridging details, rather than using the default -values.

Photovoltaic panels (PV)

SAP 10.2 now has the option to model that any electricity generated from onsite PV panels can be stored in a battery. This allows some of the electricity generated to be used within the dwelling later if it cannot be used immediately.

Furthermore, if no battery storage is present, SAP 10.2 allows for PV diverters to be modelled. PV diverters are devices which divert electrical energy from PV panels to heat water using an electric immersion heater in a hot water cylinder. Such energy is surplus to the instantaneous electrical demand of the dwelling and would otherwise be exported to the electricity grid.

PV diverters increase the amount of PV generation that can be used within the dwelling and reduce running costs to the householder by offsetting the use of the main water heating system (e.g., a gas boiler). However, it should be noted, to maximise the diversion of electricity, a dwelling with a PV diverter may store water at a higher temperature than typical practice. This could also increase cylinder heat losses this is reflected in applying a correction factor of 0.9.

What does this mean for you?

Installation of modern technologies, such as batteries and PV diverters can now assist with demonstrating compliance with Part L of the Building Regulations and savings can be recognised within the SAP calculation methodology.

Overheating risk

SAP 2012 provided a simplified methodology for assessing potential high internal temperatures in hot weather within the dwelling. However, this has been removed from SAP 10.2.

The requirement to now limit unwanted solar gains in summer and providing an adequate means of removing excess heat from the indoor environment is now controlled under Part O of the Building Regulations. Approved Document O (2021 edition) provides guidance that compliance can be demonstrated by using one of the following methods:

What does this mean for you?

A further more detailed, assessment beyond SAP is now required to demonstrate that dwellings will limit unwanted solar gains in summer and has adequate means of removing excess heat from the indoor environment.

Thermal mass parameter

Thermal mass is an attribute of the mass of the building which enables that building to store heat. Thermal mass can be a contributing principle in delivering energy performance. Thermal Mass Parameter (TMP) is a reference to the total thermal mass of the building based on its construction and is defined in SAP as the sum of (area times heat capacity) over all construction elements divided by total floor area.

In SAP 2012, where the details of the thermal mass of construction were not known precisely, an indicative value (low, medium or high) of TMP could be used instead of a detailed calculation. However, in SAP 10.2 the TMP is now required to be obtained by calculation from the actual construction elements of walls, floors, and roofs (including party and internal walls, floors, and ceilings) and kappa values as detailed in BS EN ISO 13786.

What does this mean for you?

SAP 10.2 requires the TMP to be calculated for the actual construction of the dwelling. For some designs, this may improve the energy performance of a dwelling; but for others it may not. Either way, it will improve the accuracy of modelling the energy performance of dwellings.

The future of SAP

Followingrecommendations by the Climate Change Committee (CCC)and ascoping studycommissioned by the former Department for Business, Energy and Industrial Strategy, the government is developing a new methodology to increase its accuracy, robustness, and ensure it is fit for net zero.

In December 2023, the Government published a consultation on this new methodology theHome Energy Model(closed 27 March 2024) so that industry can participate in the ongoing development process.

The Home Energy Model is still under development and its first version will be implemented alongside the Future Homes Standard in 2025.


Disclaimer:

Every care has been taken to ensure that the above content is correct at the time of publication. Any reliance on the content should be verified by the dutyholder(s) and their professional advisers. It is the responsibility of the dutyholder(s) and/or person carrying out the work to ensure compliance with the relevant building regulations and associated legislation.

This content is given in good faith by LABC. It is not definitive, and compliance will be a matter for the relevant building control authority to decide as the enforcing body for the building regulations, and ultimately for the appropriate tribunal or court to determine.

TT_23.1

This article was originally published on the LABC website on 24/11/2022. View the original article.